SoCal Dirt Movers, Fallbrook, CA • Updated
Quick answer
In unincorporated San Diego County, including Fallbrook, Bonsall, Rainbow and Valley Center, a grading permit is generally required when excavation or fill moves more than 200 cubic yards, when a cut or fill is more than 8 feet high, or when work alters a watercourse or places fill in a mapped floodway. Typical shed pads, yard leveling and driveway regrades stay under those lines.
At a glance
- Volume trigger
- Excavation or fill over 200 cubic yards
- Height trigger
- Cut or fill over 8 ft vertical
- Water trigger
- Altering a watercourse, or fill in a mapped floodway
- Who issues it
- County Planning and Development Services (PDS)
- PDS Land Development Counter
- (858) 694-2055
- Inside Temecula
- City of Temecula, not the County
When does San Diego County require a grading permit?
San Diego County generally requires a grading permit when a project crosses any one of three lines, according to the County's Grading Plan Application User Guide. The rules apply in the unincorporated county, which includes Fallbrook, Bonsall, Rainbow, the San Diego County side of De Luz, and Valley Center, where permits come from County Planning and Development Services (PDS), not a city hall.
- Volume: excavation or fill that moves more than 200 cubic yards of material.
- Height: an excavation or fill more than 8 feet in vertical height.
- Water: grading that alters land within a watercourse, affects a watercourse's flow or capacity, or places fill in a mapped floodway.
Any one of the three is generally enough. A small job in a creek can need a permit at 20 yards, and a pad with a 10-foot cut can need one well under 200 yards. Incorporated cities such as Oceanside, Vista, San Marcos and Escondido issue their own permits.
What grading is exempt from a permit?
Section 87.202 of the County Grading Ordinance exempts some work from the permit. The exemptions include:
- Excavation below finished grade for footings, basements, retaining walls, swimming pools and septic systems, when a valid building permit authorizes the work.
- Routine road maintenance: smoothing, texturing, and filling small rills and potholes, with no change to the landform, inside the existing road footprint.
- Emergency grading that the County has authorized in advance, in writing.
Exempt does not mean anything goes. Exempt work still has to meet the ordinance's slope, setback, erosion prevention and planting requirements, permit or no permit.
Do I need a grading permit for my project?
Most small homeowner projects in Fallbrook and North County typically do not need a grading permit, but pads cut into slopes and anything touching a creek often do. The table shows the usual answer for common jobs. Your lot's slope, volume and drainage decide it, so check with PDS when you are close.
| Project | Grading permit? | Why |
|---|---|---|
| Shed pad, 12 x 20 ft | Typically no | 6 inches of average cut is about 4 cubic yards. The shed itself may need a building permit; check with PDS. |
| Leveling a 2,000 sq ft backyard | Typically no | 6 inches of average cut or fill is about 37 cubic yards. Changing where water leaves the lot can still need review. |
| Regrading an existing dirt driveway | Typically no | Smoothing and filling ruts inside the existing road footprint is routine maintenance under Section 87.202. Widening or a new route is not. |
| Footings, pool or septic dig with a building permit | Typically exempt | Section 87.202 covers excavation below finished grade authorized by a valid building permit. |
| ADU pad, 1,000 to 1,200 sq ft | Depends | A flat-lot pad is usually well under 200 yards. On a slope, check the volume and cut height; it may be processed as minor grading with the building plan check. |
| Hillside cut-and-fill pad | Often yes | Volume adds up fast on a slope, and a cut or fill over 8 ft is a trigger on its own. Check with PDS. |
| French drain or swale on your own lot | Typically no | Small volumes. Work that sends water onto a neighbor, a road or a watercourse can need review. |
| Work in or along a creek or wash | Typically yes | Altering a watercourse or its flow is a trigger at any volume. Check with PDS before any machine goes in. |
How do I estimate cubic yards to know if I am near 200?
Multiply length by width by average depth in feet, divide by 27, and do it separately for the cut and the fill. If either number, or the two together, comes near 200 cubic yards, call PDS before you book a machine, because how a project is counted is the County's call. A typical example on a sloped Fallbrook lot:
- 1
Measure the pad
A 30 x 40 ft ADU pad, 1,200 sq ft, on ground that falls 8 feet across the 30-foot depth. Set the pad at the midpoint and the back edge needs 4 feet of cut and the front edge 4 feet of fill.
- 2
Find the average depth
The cut tapers from 4 feet at the back to nothing at the middle, an average of 2 feet over half the pad, 600 sq ft. The fill mirrors it on the low side.
- 3
Multiply and divide by 27
600 sq ft x 2 ft = 1,200 cubic feet, divided by 27 = about 44 cubic yards of cut, and about 44 of fill. Both are well under 200, and nothing is near 8 feet high.
- 4
Try a bigger pad
A 50 x 80 ft house and garage pad on a steeper lot, with 8 feet of cut at the back: half the pad is 2,000 sq ft at an average of 4 feet, or 8,000 cubic feet, about 296 cubic yards of cut. That is over 200 on its own, and laying the bank back above the pad makes the cut face taller than 8 feet.
- 5
Add the banks and the import
Wedge math leaves out the banks above and below the pad, so treat it as a floor. If you have to import fill, add 15 to 25 percent for compaction and waste, and remember minor grading allows no more than 200 cubic yards of import or export. The fill dirt guide has the full method.
What kinds of grading permits are there?
The County has three kinds of grading permit: agricultural, minor and major. Which one applies depends on how the land is used, how much material moves and what the grading touches.
| Permit type | When it applies | Limits and notes |
|---|---|---|
| Agricultural grading (Section 87.205) | Areas used exclusively for agricultural production | Its own permit type for working farmland and groves |
| Minor grading (Section 87.206) | A single-family home or accessory structure on a single lot | Processed with the building plan check. Up to 2,500 cubic yards, no more than 200 cubic yards of import or export, no surface water affected, no new drainage structures, no cut or fill bank over 20 ft |
| Major grading | Projects beyond the minor grading limits | Requires bonds and agreements |
Grading permits get environmental review under the California Environmental Quality Act (CEQA), and the applicant signs an At-Risk letter acknowledging that the project may need discretionary review. In plain terms, filing does not promise a quick approval, so build review time into the schedule.
Do I need a grading permit in Temecula or De Luz?
Inside Temecula city limits, grading is a City of Temecula question, handled by its Public Works and Building and Safety departments, not San Diego County. We do not quote city thresholds here; call the city before planning a pad, a retaining wall, or any change to a tract lot's engineered drainage. In Temecula tracts the HOA often has to approve the yard plan too.
In unincorporated Riverside County, which includes part of De Luz and the wine country, the authority is Riverside County Building and Safety. De Luz straddles the county line, so the first question on a De Luz job is which county the parcel sits in. More on local work in Temecula and the wine country.
What do we do, and what is left to you?
We grade to the plan and tell you when a job looks close to a threshold; we do not pull permits or do engineering. When a project has an engineer's or designer's grading plan, we set grade stakes with a laser level, cut to it, place fill in lifts and track-roll it, and coordinate compaction testing with your soils engineer when the plan calls for it.
Without a plan, we estimate the yards and cut heights from your photos or the site walk. If the numbers come near 200 cubic yards or 8 feet, or the work is near a creek or a mapped drainage, we say so before booking and you check with PDS. The permit is for you, your contractor or your engineer to pull. See grading and leveling for typical hours, ADU pad grading costs if a pad is the project, or text photos for a quote.
Questions people ask
Do I need a grading permit to level my backyard in Fallbrook?
Typically no. Leveling a 2,000 sq ft yard by about 6 inches moves roughly 37 cubic yards, far under the County's 200 cubic yard trigger, with no cut near 8 feet. It can still need County review if it changes where water leaves your lot or touches a watercourse, and it has to meet the ordinance's slope, setback and erosion rules.
Does an ADU pad need a grading permit?
It depends on the lot. A pad on a flat lot is usually well under 200 cubic yards. A pad cut into a slope can pass 200 yards or 8 feet of cut or fill. Grading for a single-family home or accessory structure can be processed as minor grading with the building plan check. Ask PDS or your designer early.
Is regrading a dirt road exempt from a grading permit?
Routine road maintenance is exempt under Section 87.202: smoothing, texturing, and filling small rills and potholes inside the existing road footprint, with no change to the landform. Widening the road, cutting a new route or building up a section with fill is different work and can need a permit. Work that alters a watercourse is its own trigger.
Who pulls the grading permit, the owner or the operator?
Usually the property owner, the general contractor or the project's engineer handles the application with County PDS. We do not pull permits or prepare grading plans. We grade to the approved plan, set grade stakes to its elevations, and coordinate compaction testing with your soils engineer when the plan requires it. The PDS Land Development Counter is (858) 694-2055.
How do I find out if my project needs a permit before I start?
Estimate your cut and fill in cubic yards, the tallest cut or fill in feet, and whether any work is near a creek or wash. Then call the County PDS Land Development Counter at (858) 694-2055 with those numbers and your parcel number. Inside Temecula city limits, call the City of Temecula instead, and check with your HOA.
Does grading on an avocado grove need a permit?
Agricultural grading has its own permit type under Section 87.205, for areas used exclusively for agricultural production. Pulling dead trees is different work from cutting new terraces or roads, so describe the work, the volumes and any creek nearby to PDS and ask what applies. If the cleared grove is becoming a house pad, it is no longer agricultural grading.
Sources
- County of San Diego PDS, Grading Plan Application User Guide
- County of San Diego Planning and Development Services
- City of Temecula
Rules change. Check with the agency before you rely on a deadline or a threshold.
How these numbers are worked out. Labor is our published rate, $150 per hour with a 4-hour minimum, times the hours these jobs typically take on normal ground. Material prices are typical delivered prices from North County yards and change with the yard and the distance. For a number on your job, text photos to (442) 271-2748 or send the estimate form.
