SoCal Dirt Movers, Fallbrook, CA • Updated
Quick answer
Trenching in Fallbrook and North San Diego County costs about $4 to $6 per foot for an 18- to 24-inch water, electrical or irrigation trench in normal soil, because the mini excavator cuts 100 to 150 feet in the 4-hour, $600 minimum. Groves run about $8 to $12 per foot. Backfill after inspection is 2 to 4 hours more, billed separately.
At a glance
- Normal soil
- $4 to $6 per foot, 100 to 150 ft in 4 hours
- Through a grove
- About $8 to $12 per foot
- Minimum
- 4 hours, $600
- Backfill after inspection
- 2 to 4 hours, billed separately
- ADU water, sewer and power
- 6 to 12 hours, $900 to $1,800
- Before digging
- 811 ticket, 2 working days ahead
How much does trenching cost per foot?
Trenching costs about $4 to $6 per foot in normal Fallbrook soil for a water, electrical or irrigation trench 18 to 24 inches deep. The mini excavator cuts 100 to 150 feet in four hours, and four hours is the $600 minimum, so $600 divided by 100 to 150 feet is $4 to $6 a foot. The work is billed by the hour, not the foot; the per-foot figure is the hours divided by the length.
| Job | Depth (set by the trade) | Soil | Feet per 4 hours | Cost per foot |
|---|---|---|---|---|
| Water service | 18 in | Normal DG | 100 to 150 | $4 to $6 |
| PVC electrical conduit | 18 in | Normal DG | 100 to 150 | $4 to $6 |
| Direct-burial cable | 24 in | Normal DG | 100 to 150 | $4 to $6 |
| Irrigation mainline | 12 to 18 in | Normal DG | 100 to 150 | $4 to $6 |
| Any of the above | 12 to 24 in | Avocado or citrus grove | 50 to 75 | $8 to $12 |
| Any of the above | 12 to 24 in | Rocky DG with boulders | About 60 to 100 | About $6 to $10 |
| Ledge rock | Any | Needs the hydraulic breaker | Billed by the hour once hit | Varies |
How deep does each trench need to be?
The depth is set by the trade and the inspector, not by us, and in Fallbrook it is not set by frost. Local plumbers usually ask for 18 inches on a water service, electricians for 18 inches on PVC conduit and 24 inches on direct-burial cable, and irrigation contractors for 12 to 18 inches on a mainline. Depth is measured to the top of the pipe or cable, so the trench is cut a little deeper, plus any sand bedding the line calls for.
Width follows the bucket. The mini excavator carries 12, 18 and 24 inch trenching buckets, and a single water line or conduit usually fits the 12-inch. Get the depth and width from your plumber or electrician before we dig, so the inspector has nothing to say.
What does an ADU utility trench cost?
Trenching water, sewer and power to a new ADU typically takes 6 to 12 hours, $900 to $1,800, before backfill. The range is wide because ADU runs vary: a detached unit 50 feet behind the house in a flat yard sits at the low end, and one 200 feet down a slope with a sewer line that needs steady fall sits at the high end.
The trades decide whether lines share a trench, and how far apart they sit; we cut what the plan shows. Sewer depth follows the fall the line needs back to the main or the septic system, so the plumber sets it on site. If the pad is not graded yet, both jobs can go on one visit; see ADU pad grading costs.
Is backfill included in the trench price?
No. Backfill after inspection is billed separately, usually 2 to 4 hours, $300 to $600. The usual sequence: we cut the trench and pile the spoil on one side, the trade lays the line, the inspector signs it off, and we backfill in lifts, track-roll it with the Bobcat and rake the surface so the line is hard to find a month later.
If the inspection happens the same day, we stay and close the trench that afternoon. Sand bedding, when the line calls for it, is material at cost, and the Bobcat carries it to the trench. Details are on our trenching service.
Do I need to call 811 before trenching?
Yes. California Government Code 4216.2 requires a DigAlert notification through 811, which is free, at least 2 working days before digging, not counting the day you call, and not more than 14 calendar days before. Outline the trench in white paint first; California requires it. The ticket is valid for 28 days and can be renewed.
Within 24 inches on either side of a marked line, digging is by hand tools only until the line is exposed. 811 marks lines owned by member utilities, generally up to the meter. Private lines are not marked: the water line from the meter to the house, power to a well, barn or gate, sprinklers and the septic system. A private locating service can find them, and we hand-dig around any line you tell us about. The full timeline and color code are in how 811 works in California.
Should I rent a trencher or hire an excavator?
Hire the excavator in most of Fallbrook, Bonsall and Valley Center, because a walk-behind trencher stalls in hard-packed decomposed granite, in granite boulders and in grove roots, and that is what most local ground is made of. A trencher cuts a narrow slot with a digging chain. In soft, rock-free soil it is quick. Here it tends to hit the first buried boulder, buck, and stop, leaving you with a rental bill and half a trench.
The mini excavator's tooth bucket cuts the hard DG, the thumb lifts the boulders out, and root cuts through a grove are clean. A 100-foot run is $600 and finished in a morning. Renting makes sense on a long run in soft ground, like the sandy loam on parts of the Bonsall valley floor, if you are comfortable running the machine and the 811 ticket is in hand. More on that trade-off in renting vs hiring an operator.
What do typical trench jobs cost, start to finish?
Three typical examples, worked out the way the quote is written. Hours depend on the ground we find, and we tell you as soon as it changes.
- 1
100-foot water line to a barn: about $900 to $1,200
Normal DG, 18 inches deep, 12-inch bucket. The trench fits in the 4-hour minimum: $600, or $6 a foot. Backfill after the inspection is 2 to 4 hours, $300 to $600. Total about $900 to $1,200, or $9 to $12 a foot with backfill.
- 2
300-foot electrical run to a well pump: about $1,200 to $2,400
Conduit at 18 inches across pasture and a driveway shoulder. At 100 to 150 feet per 4 hours that is 8 to 12 hours; on clean, open ground it can run closer to the 200-foot conduit pace, as little as 6 hours. Call it 6 to 12 hours, $900 to $1,800, or $3 to $6 a foot. Backfill 2 to 4 hours, $300 to $600. Total about $1,200 to $2,400.
- 3
200-foot irrigation run through an avocado grove: about $1,950 to $3,000
Grove trenching runs about half the footage per hour, 50 to 75 feet per 4 hours, because the route weaves between tree rows and every root gets a clean cut. 200 feet is about 11 to 16 hours, $1,650 to $2,400, roughly $8 to $12 a foot. Backfill 2 to 4 hours, $300 to $600. Total about $1,950 to $3,000.
Questions people ask
Is there a minimum charge for a short trench?
Yes, the 4-hour minimum, $600. A 30-foot trench to a gate costs the same as a 100-foot one, so short runs are where the per-foot price looks worst. Bundle them: a gate line, a downspout run and a hose bib line on the same visit share one minimum, and so does a shed pad or a drainage swale done the same morning.
Can water and electrical lines share one trench?
Sometimes, but that is the trades' and the inspector's decision, not ours. Electrical and plumbing codes set rules for separation between lines in a shared trench, and your plumber and electrician know what the local inspector expects. Tell us what they agree on and we cut one wider trench or two separate ones to match.
How wide is the trench?
As narrow as the line allows. The mini excavator carries 12, 18 and 24 inch trenching buckets, and a single water line or conduit usually goes in the 12-inch. A wider bucket goes on when lines share a trench, when sand bedding needs room, or when the trade asks for it. A narrower trench means less spoil, less backfill and less disturbed ground.
Does 811 mark the line from my meter to my house?
No. DigAlert marks lines owned by member utilities, which generally stop at the meter. The water line from the meter to the house, power to a well or barn, irrigation and septic lines are private and are not marked. A private locating service can find them, and anything you tell us about we hand-dig around.
How long can a trench stay open before inspection?
Until the line is installed and inspected, which depends on your trade and the inspector's schedule. An open trench is a hazard to kids, pets and horses, so we pile spoil on one side, back from the edge, and you should flag it where people walk. Rain is the other risk: DG trench walls can slough in a storm and need cleaning out before the line goes in.
Is hand digging cheaper for a short trench?
For 20 or 30 feet in soft soil, it can be. In Fallbrook's compacted DG and boulders, hand digging 18 inches deep is slow, hard work, and a 100-foot run takes most people a weekend or more. At $600 for the machine, the trade-off is how much your weekend is worth. Hand digging is also the rule within 24 inches of any marked line.
Sources
- California Government Code 4216.2 (811 notification)
- DigAlert, Underground Service Alert of Southern California
Rules change. Check with the agency before you rely on a deadline or a threshold.
How these numbers are worked out. Labor is our published rate, $150 per hour with a 4-hour minimum, times the hours these jobs typically take on normal ground. Material prices are typical delivered prices from North County yards and change with the yard and the distance. For a number on your job, text photos to (442) 271-2748 or send the estimate form.